Organisation: Sub Contractor to Worley Parsons

Project: APLNG Post IFC Piping design

Project Tenure: 1 Months

Project Type: Green Field

Client: APLNG

Characteristics: Origin is building a Pipeline Gas Compression station at two locations Talinga and Spring Gully.  Talinga Piping design was completed and Issued for Construction without obtaining all Vendor data on client request.  This project was to obtain Vendor data, carry out Pipe Stress Analysis and finalise the project.

Responsibilities:

  • Pipe Stress Analysis
  • Pipe Isometric verification and checking
  • Liaison with client
  • Liaison with vendor