Organisation: Sub Contractor to Worley Parsons

Project: GLNG Interconnect Facility Project

Project Tenure: 4 Months

Project Type: Green Field

Client: Santos

Characteristics: Santos and QGC are planning to share / transfer gas with each other and a metering and interconnect piping was required to facilitate this.  High Pressure Class 600 and Class 900 piping with low temperature services were designed for this project.

Responsibilities:

  • Pipe Stress Analysis
  • Pipe Isometric verification and checking
  • Flange Leakage Design based on ASME Section VIII Division 1 and Division 2
  • Material Take-Off (MTO) generation
  • Providing Technical Bid Evaluation (TBE)
  • Purchase Requisition generation
  • Liaison with internal and clients
  • Liaison with vendor