Organisation: Sub Contractor to Worley Parsons Project: GLNG Interconnect Facility Project Project Tenure: 4 Months Project Type: Green Field Client: Santos Characteristics: Santos and QGC are planning to share / transfer gas with each other and a metering and...
Recently for a project we were having problems with Isogen to generate Piping Isometric but it was not working well. This was required for me to carryout Pipe Stress Analysis based on the information in Stress Isometrics. I searched CaesarII help and found out that...
Stress Analysis forms integral part of Pipe Design. A checklist spreadsheet is provided to ease the process of deciding which pipes to stress analyze. Engineering judgement should be made while using this spreadsheet To download the spreadsheet right-click the button...
Organisation: Working for AECOM Australia Pty Ltd Project: Secondment to Queensland Nickel Yabulu RefineryProject Tenure: 1 year Project Type: Brown Field Client: Queensland Nickel Yabulu Refinery (QNI) Characteristics: Yabulu Refinery is over 30 years old with a...
Organisation: Working for AECOM Australia Pty Ltd Project: Slurry Pipeline (Design) Project Tenure: 2 months Project Type: Green Field Client: Queensland Nickle Characteristics: Existing Slurry pipe is around 500m long but had Victaulic and Dresser Couplings along its...